Incentive on Connections Engagement (ICE)
Service improvement work plans
LV
HV
HV
HV
LV
HV
LV
HV
HV
HV
HV
HV
HV
HV
HV
HV
HV
LV
HV
HV
HV

Assessment and Design (A&D) fees
We continued to support and contribute to the national debate on the introduction of A&D fees and keep our customers informed of the outcomes. On conclusion of the industry-wide consultation, we implemented changes to our existing policies or practices and communicated these to our customers.

Assessment and Design (A&D) fees
We continued to support and contribute to the national debate on the introduction of A&D fees and keep our customers informed of the outcomes. On conclusion of the industry-wide consultation, we implemented changes to our existing policies or practices and communicated these to our customers.
HV
HV
HV
HV
HV
HV
HV

Flexible connections
We published information on flexible connections for stakeholders considering this type of arrangement, including any changes necessitated by the Access and Forward-looking Charges Significant Code Review.

Flexible connections
We published information on flexible connections for stakeholders considering this type of arrangement, including any changes necessitated by the Access and Forward-looking Charges Significant Code Review.
LV

Technical guidance for contractors and installers
We will develop an online knowledge base for installers and electrical contractors, with practical guidance and technical information.
HV

ENA good practice guide
We said we would participate in the development of the ENA good practice guide on implementation of standard milestones for connection contracts.

ENA good practice guide
We said we would participate in the development of the ENA good practice guide on implementation of standard milestones for connection contracts.
LV

Updates to our alternative provider register
We made changes to the alternative provider register on our website so that ICPs who are authorised to self-determine points of connection and self-approve designs are clearly identifiable to customers looking to appoint an ICP to carry out contestable works.

Updates to our alternative provider register
We made changes to the alternative provider register on our website so that ICPs who are authorised to self-determine points of connection and self-approve designs are clearly identifiable to customers looking to appoint an ICP to carry out contestable works.
LV
HV
LV
HV
HV
HV
HV
HV
Incentive on Connections Engagement (ICE)
Service improvement work plans
Connections 101 sessions
End date: March 2023
Engagement with ICPs and IDNOs
End date: March 2023
Engaging with connections stakeholders
End date: March 2023
Pre-application support
End date: March 2023
Network development and investment
End date: March 2023
Network data sources
End date: March 2023
Network data requests
End date: March 2023
Network constraints
End date: March 2023
Known network constraints
End date: March 2023
EV connections guidance
End date: December 2022
Flexible connections
End date: December 2022
Innovation
End date: March 2022
Enabling competition
End date: March 2022
Provision of information
End date: March 2022
Provision of information
End date: March 2022
Provision of information
End date: March 2022
Improving our communication and engagement
End date: March 2022
Technical and commercial developments
End date: March 2022
Provision of information
End date: March 2022
Technical and commercial developments
End date: March 2022
Provision of information
End date: February 2022
Technical and commercial developments
End date: December 2021
Improving our application and delivery processes
End date: October 2021
Accelerated Loss of Mains Change Programme
End date: March 2021
Providing timely and accurate information for generators on planned outages
End date: March 2021
Stakeholders will be better informed and find it quicker and easier to make applications for different types of LCTs.
End date: March 2021
Developing our budget estimating tool
End date: March 2021
Engaging with connections stakeholders as we transition to a DSO
End date: March 2021
We will engage with stakeholders on the electrification of heating and our role in the low carbon transition
End date: March 2021
We will continue to engage with stakeholders about the actions we are taking to support the roll-out of Electric Vehicles (EVs) in our region and on our role in the low carbon transition
End date: March 2021
Support for Community Energy groups and stakeholders
End date: March 2021
Local energy planning forums
End date: March 2021
Streamlining our application process
End date: March 2021
Pre-application surgeries for planners and developers
End date: March 2021
Engaging with installers of Low Carbon Technologies (LCTs)
End date: February 2021
IDNO engagement
End date: January 2021
Engaging with stakeholders to inform our Distribution Future Energy Scenarios.
End date: December 2020
Heat map data
End date: November 2020
Updates to our alternative providers register
End date: November 2020
IDNO connections
End date: November 2020
Guide for Local Authorities and LEPs
End date: September 2020
Engaging with customers with poor power factor
End date: March 2020
Local government forums
End date: March 2020
Our transition to a Distribution Systems Operator (DSO)
End date: March 2020
Next steps to faciliate the roll-out of Electric Vehicles (EVs) in our region
End date: February 2020
Connections surgeries
End date: February 2020
LV budget estimating tool
End date: January 2020
Connections contact guide
End date: December 2019
New Electric Vehicle (EV) connections guide
End date: December 2019
Training for heat map users
End date: December 2019
Updates on Statement of Works process and Appendix G
End date: November 2019
Extending the scope of contestable works
End date: November 2019
Customers who connect through a third party
End date: October 2019
SafeDig
End date: September 2019
Active Network Management (ANM) and future solutions
End date: March 2019
Our transition to a distribution system operator (DSO)
End date: March 2019
Network constraint and curtailment information
End date: March 2019
Knocked down telecommunications street furniture
End date: March 2019
DG owner operator forum
End date: March 2019
The Transmission/Distribution interface and Statement of Works process
End date: March 2019
Self-service budget tool
End date: March 2019
Better technical guidance for generators.
End date: March 2019
Connection offer expiry dates
End date: February 2019
Continued engagement on A&D fees
End date: February 2019
Improved customer communications
End date: February 2019
Applying for a temporary site supply
End date: January 2019
Hard to reach connections stakeholders
End date: December 2018
Legal agreements for ICPs
End date: November 2018
Our engagement with flexibility service providers
End date: November 2018
New Electric Vehicle (EV) connections
End date: November 2018
Access to network information
End date: September 2018
Network information
End date: September 2018
Contact information for connection engineers
End date: September 2018
DG connections guide
End date: September 2018
Self-service adoption agreements for ICPs
End date: August 2018
Updates on our connections offers
End date: July 2018
More targeted communications
End date: June 2018
Assessment and Design (A&D) fees
End date: March 2018
TSO/DSO roles
End date: March 2018
T/D interface
End date: March 2018
Timescales for protection settings
End date: March 2018
Standard suite of storage service offers.
End date: March 2018
Social media
End date: March 2018
Undergrounding of networks in areas of outstanding natural beauty (AONB)
End date: March 2018
Find my MPAN online service
End date: March 2018
Energy storage case studies
End date: March 2018
Active Network Management (ANM)
End date: March 2018
Connections workshops
End date: March 2018
EHV quotations
End date: January 2018
Connecting Low-Carbon Technologies (LCTs).
End date: December 2017
Storage applications
End date: December 2017
Distributed generation connectons
End date: December 2017
Digital communications
End date: September 2017
Distribution Network Operator (DNO) to Distribution System Operator (DSO)
End date: September 2017
ICP design matrix
End date: September 2017
Independent inspections
End date: September 2017
Access to mains records
End date: August 2017
Implementaton of contract milestones
End date: August 2017
Contracted capacity register
End date: July 2017
Multi-optioneering application service
End date: July 2017
Schedule of rates for input services
End date: July 2017
ICP design approvals
End date: June 2017
ICP input services
End date: June 2017
Assessment and design (A&D) fees
End date: March 2017
Contract milestones
End date: March 2017
Connecting new and innovative technologies
End date: March 2017
Constrained networks
End date: March 2017
Contract milestones
End date: March 2017
Contracted capacity register
End date: March 2017
Capacity clawback
End date: March 2017
ICP design approvals
End date: March 2017
Transmission/Distribution (T/D) interface
End date: March 2017
ICP quotations
End date: March 2017
ICP self-determination point of connection (POC)
End date: March 2017
Provision of information on wayleaves
End date: March 2017
Part-funded reinforcement
End date: March 2017
Heat maps
End date: March 2017
Converting budget estimates into firm quotations
End date: December 2016
Connections case studies
End date: December 2016
ICP design approvals
End date: December 2016
Single points of contact
End date: December 2016
Release of unused network capacity
End date: December 2016
Re-connection of knocked down street lighting
End date: December 2016
Protection policy and small scale connections
End date: December 2016
Metered disconnections as business-as-usual
End date: December 2016
Contract milestones
End date: November 2016
Protection policy
End date: November 2016
Stakeholder updates
End date: October 2016
Understanding technical terminology
End date: September 2016
Metered disconnection trial
End date: September 2016
Export limiting schemes
End date: July 2016
Active network management (ANM)
End date: May 2016
Sharing our smart grid strategy
End date: May 2016